The most important new generation coming to the US grid over the next three years was never filed in an interconnection queue. It was filed in a decommissioning plan.
Three shuttered nuclear plants are being brought back to life: Palisades in Michigan, the Crane Clean Energy Center (formerly Three Mile Island Unit 1) in Pennsylvania, and Duane Arnold in Iowa. Together they represent about 2.25 GW of firm, around-the-clock capacity, all expected back on the grid by the end of this decade. Each one is returning on the strength of interconnection rights it already holds, while brand new projects wait years just to be studied.
That contrast is the story. New generation in the United States now takes an average of about five years to move from interconnection request to commercial operation, up from less than two years in 2008, according to research from Lawrence Berkeley National Laboratory. In PJM, where two of the three restarts sit, projects have waited an average of more than five years, and the operator's newly reopened queue is studying more than 800 projects totaling 220 GW in its first cycle alone. In MISO, home of Duane Arnold, study cycles are running three to four years, with a four-year backlog still being worked through.
| Years | Years |
|---|---|
| New PJM gas plant (2026 entry) | 7 |
| Average new US project | 5 |
| Nuclear restarts (existing rights) | 0 |
Source: Lawrence Berkeley National Laboratory; Load Factor analysis
The restarted plants skip most of that. A retired nuclear plant still has its switchyard, its transmission connections, and its interconnection service history. Returning it to service is a matter of NRC licensing, refurbishment, and a willing buyer, not a new position at the back of the queue.
The clearest public example of how this works is Crane. Constellation filed an interconnection request with PJM, but it did not simply join the queue. In June 2026, the Federal Energy Regulatory Commission granted Constellation a waiver to transfer capacity interconnection rights from two units at its Eddystone plant in Pennsylvania, units that had been scheduled to close, to support Crane's 835 MW return. Existing grid access, in other words, is a transferable asset.
Here is what the restart wave looks like plant by plant.
Palisades, owned by Holtec International in Covert Township, Michigan, is the furthest along. The roughly 800 MW pressurized water reactor shut down in May 2022 after 50 years of operation, was defueled, and was headed for decommissioning. Holtec reversed course in late 2023. The Department of Energy finalized a $1.52 billion loan guarantee in September 2024, the Nuclear Regulatory Commission reinstated the plant's operating license in August 2025, and fuel loading began in August 2026. It would be the first plant in US history to restart after entering decommissioning.
Crane Clean Energy Center is next. Constellation shut Three Mile Island Unit 1 in 2019 for economic reasons, well before its license expired. A 20-year power purchase agreement with Microsoft, signed in September 2024, underwrites the restart, and DOE closed a $1 billion loan in November 2025 toward Constellation's roughly $1.6 billion reinvestment. The 835 MW plant is targeting a return between 2027 and 2028, which would put it on the grid years ahead of any new gas plant entering PJM's current queue.
Duane Arnold is the largest federal bet. NextEra's 615 MW plant in Palo, Iowa, closed in 2020 after storm damage accelerated a planned retirement. DOE closed a loan of up to $1.9 billion on September 8, 2026, to finance the restart, which NextEra targets for the first quarter of 2029. Google signed a 25-year power purchase agreement to take the plant's output for its Iowa data centers.
| MW | MW |
|---|---|
| Crane | 835 |
| Palisades | 800 |
| Duane Arnold | 615 |
Source: Company filings; Load Factor analysis
Put together, that is 2,250 MW of baseload capacity with defined timelines and creditworthy buyers. For comparison, analysts estimate that a new gas plant entering PJM's reformed queue process today would not generate power before 2033, given study timelines and turbine backlogs.
The restarts are part of a broader pattern: the grid's most valuable asset right now is not a new turbine, it is an existing interconnection. Meta's 20-year agreement to take 1,121 MW from Constellation's Clinton plant in Illinois, beginning June 2027, is about keeping an operating plant alive rather than a restart, but the logic is identical. Constellation won a 20-year license renewal for Clinton and for its Dresden plant in December 2025. The NRC approved a 20-year extension for California's Diablo Canyon in April 2026, though the state has only authorized operations through 2030 so far. None of these need the queue.
The lesson for anyone tracking US generation is straightforward. The interconnection queue tells you what might get built. Existing interconnection rights, license renewals, and restarts tell you what is actually coming. Watch the second list. It is moving faster.