Nearly two-thirds of the queue never gets built

Published November 3, 2026 • 2 min read • Load Factor team
Share this

America's interconnection queue looks enormous. Most of it will never get built.

Load Factor's queue data, queried Nov 3, 2026, tracks 38,128 projects totaling 5,284 GW, including withdrawn projects. Of those, 24,170 projects (3,183 GW) have withdrawn. That is over 63% of tracked projects and over 60% of tracked capacity gone before construction.

The live pipeline is much smaller: 13,323 projects totaling 1,985 GW. Anyone quoting the full queue as future capacity is counting a graveyard.

ERCOT holds the largest live pool: 2,290 projects totaling 454 GW, more than three times PJM's live 1,850 projects at 139 GW (PJM figures are capacity MW, not nameplate). And ERCOT is still growing. The Nov 3 refresh added 27 new ERCOT projects totaling 4.9 GW.

Movement cuts both ways. In the same Nov 3 refresh, two PJM solar projects on the same Lancaster County, Virginia line moved to Under Construction: AG1-038 (18 MW) and AF1-042 (17 MW), both on the Garner DP-Lancaster 115 kV line, in Dominion territory. They entered the queue in 2020 and 2019, and both are slated for service in late 2027. Small projects, long waits, now moving. Their developers are shown as inferred attributions: Rappahannock Solar, LLC and WALLER SOLAR I, LLC.

The lesson is not that the queue is empty. It is that the queue is two different things: a large withdrawn history and a smaller live pipeline. Telling them apart, project by project, is the work.

Method note: totals are rounded down. Withdrawn-included totals count every tracked project; live totals exclude withdrawn projects. PJM MW figures are capacity MW (capacity interconnection rights), not nameplate. Queue status reflects the last ISO snapshot. Developer attributions carry confidence words; the two Lancaster developers above are inferred, not confirmed.

Sources

  • Load Factor interconnection queue data, queried Nov 3, 2026 (totals by status and ISO; project records AG1-038 and AF1-042)
  • Load Factor updates feed, Nov 3, 2026 (27 new ERCOT projects, 4.9 GW; two PJM projects moved to Under Construction)
Tracked queue projects: withdrawn vs live Withdrawn-included total: 38,128 projects
ProjectsProjects
Withdrawn24,170
Live13,323

Source: Load Factor queue data, Nov 3, 2026

Load Factor tracks 38,000+ interconnection queue projects, withdrawn included, across 16 North American markets, with the evidence behind every developer it names.

Next step

See your market in 30 minutes.

A walkthrough of the projects, developers and evidence in the markets you work in.

Get the weekly brief

Queue movement, newly identified developers and the week’s deals, every Monday. Read past issues

Book a 30-min walkthrough