Queue Analysis

The Gas Comeback: Data Centers Are Pulling 100+ GW of Gas Into the Queue

Published September 23, 2026 • 2 min read • Load Factor team
Share this

On September 21, North Carolina regulators denied Duke Energy a permit for a 250-MW gas turbine meant to power Amazon's $10 billion data center campus. Three Republican appointees voted no. Duke's load forecast was unvetted, nobody showed data centers would pay, and the plant clashed with the White House Ratepayer Protection Pledge. The turbines are sold out, the queues are filling with gas, and now the politics of who pays is the gating item.

The numbers behind the comeback:

PJM Cycle 1 queue requests by fuel (GW) GW
GWGW
Natural gas105.8
Storage67.5
Nuclear17.9
Solar14.8
Solar+storage hybrid8.9
Wind4.7

Source: PJM

  • Gas queue capacity jumped 86% in 2025, after 72% in 2024, while solar, wind, and storage entries all shrank (LBNL).
  • PJM's first reformed queue cycle drew 220 GW of requests. Gas was the largest fuel at 105.8 GW across 157 projects, about 48% of the total.
  • MISO's fast-lane queue class is roughly 70% gas. In ERCOT, monthly gas queue entries tripled after the OBBBA.
US gas queue capacity growth %
Category%
202472
202586

Source: LBNL

  • The equipment is gone. GE Vernova holds 116 GW of turbine orders and reservations and is taking reservations for 2031 delivery. Siemens Energy holds 87 GW with waits up to four years.
  • PJM's December capacity auction missed its reliability target for the first time ever. Data center load forecasts drove about 40% of the $16.4 billion cost.

Two tracks, one grid. Renewables and storage still dominate queue volumes, but gas is the only fuel growing, it moves through queues faster, and it clears 43 to 45% of PJM capacity auctions against about 1% for solar. The build signal is the strongest in PJM history. The binding constraints are now physical (turbines) and political (who pays).

What to watch: FERC's large-load tariff rulings after the June show-cause orders, the uncapped PJM capacity auction, and whether more states follow North Carolina in making data centers prove they will pay.

Sources

Load Factor tracks 38,000+ interconnection queue projects, withdrawn included, across 16 North American markets, with the evidence behind every developer it names.

Next step

See your market in 30 minutes.

A walkthrough of the projects, developers and evidence in the markets you work in.

Get the weekly brief

Queue movement, newly identified developers and the week’s deals, every Monday. Read past issues

Book a 30-min walkthrough