On Friday, FERC largely rejected PJM's plan for connecting data centers and other large loads to the grid. The core of the proposal, the Interim Resource Adequacy Service (IRAS) framework, would have let large loads connect without matching new capacity as long as they agreed to be curtailed ahead of grid emergencies. FERC said no: the framework intrudes on state jurisdiction over retail rates and discriminates against large loads.
This is the second time in five weeks FERC has sent PJM back to the drawing board. In early September the commission told PJM to postpone and revise its backstop procurement auction for a pending capacity shortfall.
What survived the ruling matters more than what died. FERC approved PJM's definition of large loads and ordered a large-load registry: a facility-level record of location, ramp schedule, and capacity supply. That registry is a new public data source. For anyone tracking where load is actually landing, it will be worth watching.
The PJM fight is one front in a bigger campaign. On June 18, FERC issued show-cause orders to all six US grid operators (PJM, MISO, SPP, CAISO, ISO-NE, NYISO), giving them 60 days to justify their large-load interconnection tariffs or file reforms. The commission named five reform areas: study processes, cost allocation, co-location, flexible-load services, and evaluation of nearby generation. It reviewed 3,500 pages of comments. The orders cover markets serving roughly 200 million Americans.
MISO moved first. On October 2 it asked FERC for a 120-day large-load interconnection study process, with a 15-year pairing requirement tying specific generation to specific load. FERC is expected to rule by December 2.
The supply side is already responding. When PJM reopened its queue under the reformed process this spring, more than 800 projects totaling about 220 GW applied:
| Category | Projects |
|---|---|
| Battery storage | 349 |
| Natural gas | 157 |
| Solar | 142 |
| Wind | 65 |
| Solar-storage hybrid | 45 |
| Nuclear | 45 |
| Hydropower | 11 |
Source: Reuters (PJM begins processing new power plant projects, April 29, 2026)
Three things queue watchers should take from this:
- Load is getting its own queue discipline. The same medicine generation queues got under Order 2023 (readiness milestones, financial commitments, anti-speculation filters) is now being prescribed for load. FERC explicitly wants filters that separate real projects from speculative requests.
- Cost allocation is the fight underneath. Who pays for grid upgrades driven by data centers determines how many queued projects survive. Watch how each RTO answers FERC's cost-shifting questions. That is where withdrawals will come from.
- New data is coming. A facility-level large-load registry with ramp schedules is exactly the kind of dataset that makes load forecasting honest. If MISO's 120-day track goes live early next year, there will be a second, faster dataset to track alongside the generation queue.
Jefferies analysts read the PJM ruling as bullish for independent power producers: higher capacity prices for longer. Constellation, NRG, Talen, and Vistra stand to benefit while the rules get rewritten.
The through line: interconnection data is no longer just about generation queues. Load queues are being built in real time, and the next year of FERC dockets will decide what they look like.
Sources: Utility Dive (FERC rejects most of PJM's large load interconnection plan, Oct 9 2026), Data Center Knowledge (FERC Targets Grid Rules for Data Centers, Large Loads), Parallax Nexus (MISO Asks FERC for 120-Day Large Load Interconnection Study), GCN (FERC orders all six US grid operators to justify or reform large electric load interconnection rules); Reuters (PJM begins processing new power plant projects, April 29, 2026).