California's Offshore Wind Pipeline Is Being Bought Out, Lease by Lease

Published October 17, 2026 • 3 min read • Load Factor team
Share this

California's offshore wind pipeline is shrinking one buyout at a time, and the gigawatts leaving have no replacement named.

On June 17, 2026, the Department of the Interior announced it would pay Invenergy $765 million to terminate four offshore wind leases across the New York Bight, California's Central Coast, and the Gulf of Maine. The money is being redirected to natural gas-fired plants across five Midwest states and geothermal projects in the West.

The California piece of that deal was the Morro Bay lease. Invenergy paid more than $111 million for it in 2022, planning up to 2 GW of capacity. California's attorney general and the California Energy Commission are now suing, calling the arrangement an unlawful buyout.

It is not the only exit. A $120 million buyout took out Golden State Wind's lease in the Morro Bay Wind Energy Area. RWE has reportedly received $1.2 billion to give up three leases, including its Humboldt lease. A separate $928.3 million agreement with TotalEnergies, announced in March, is facing a court challenge from state attorneys general.

The infrastructure underneath is going too. In August 2025, the administration withdrew a $426.7 million federal grant to the Humboldt Bay Harbor District for the onshore port terminal the Humboldt projects need.

Add it up: leases in both California Wind Energy Areas bought out or under litigation, no federal funding for the port terminal, and no tax credit. Modo Energy's read is blunt: there is a limited credible path for these projects to reach commercial operation by the expected mid-2030s target date.

For California's grid, the math is unforgiving. Offshore wind was supposed to be the clean, high-capacity-factor answer to evening ramps and long-duration shortfalls. Every lease that exits is capacity the state must now find elsewhere, in a queue already crowded with solar and storage competing for the same interconnection.

What to watch: whether the litigation restores any of the leases, and what California's planners pencil in to replace up to 2 GW of Morro Bay capacity that may never get built.

Federal buyouts of US offshore wind leases, 2025-2026 $ million
CategoryBuyout amount ($ million)
RWE (3 leases, reported)1,200
TotalEnergies928.3
Invenergy (4 leases)765
Golden State Wind120

Source: Modo Energy Weekly Dispatch, Oct 16, 2026; Marine Log, Jun 18, 2026. RWE figure reported, not officially confirmed.

Sources

  • Modo Energy, Weekly Dispatch (Oct 16, 2026): DOI paid Invenergy $765M (announced Jun 17, 2026) to terminate four offshore wind leases (NY Bight, Central Coast CA, Gulf of Maine), funds redirected to gas-fired and geothermal projects; $120M Golden State Wind buyout (Morro Bay Wind Energy Area); RWE reportedly received $1.2B for three leases including Humboldt; $426.7M Humboldt Bay Harbor port grant withdrawn Aug 2025; limited credible path to commercial operation by mid-2030s.
  • Marine Log (Jun 18, 2026): Interior in $765M offshore wind buy-out deal with Invenergy; $928.3M TotalEnergies agreement announced March 2026 now facing court challenge. https://www.marinelog.com/offshore/offshore-wind/interior-in-765m-offshore-wind-buy-out-deal-with-invenergy/
  • Washington Examiner (Sep 2026): California suing over the Invenergy deal; Invenergy paid $111M+ for the California lease in 2022, planned up to 2 GW. https://www.washingtonexaminer.com/policy/energy-and-environment/4737667/california-sues-trump-over-deal-cancel-offshore-wind-projects/
  • ts2.tech (Jun 17, 2026): Trump administration agrees to $765M exit from Invenergy offshore wind leases. https://ts2.tech/en/trump-administration-agrees-to-765-million-exit-from-invenergy-offshore-wind-leases/

Load Factor tracks 38,000+ interconnection queue projects, withdrawn included, across 16 North American markets, with the evidence behind every developer it names.

Next step

See your market in 30 minutes.

A walkthrough of the projects, developers and evidence in the markets you work in.

Get the weekly brief

Queue movement, newly identified developers and the week’s deals, every Monday. Read past issues

Book a 30-min walkthrough