California's offshore wind pipeline is shrinking one buyout at a time, and the gigawatts leaving have no replacement named.
On June 17, 2026, the Department of the Interior announced it would pay Invenergy $765 million to terminate four offshore wind leases across the New York Bight, California's Central Coast, and the Gulf of Maine. The money is being redirected to natural gas-fired plants across five Midwest states and geothermal projects in the West.
The California piece of that deal was the Morro Bay lease. Invenergy paid more than $111 million for it in 2022, planning up to 2 GW of capacity. California's attorney general and the California Energy Commission are now suing, calling the arrangement an unlawful buyout.
It is not the only exit. A $120 million buyout took out Golden State Wind's lease in the Morro Bay Wind Energy Area. RWE has reportedly received $1.2 billion to give up three leases, including its Humboldt lease. A separate $928.3 million agreement with TotalEnergies, announced in March, is facing a court challenge from state attorneys general.
The infrastructure underneath is going too. In August 2025, the administration withdrew a $426.7 million federal grant to the Humboldt Bay Harbor District for the onshore port terminal the Humboldt projects need.
Add it up: leases in both California Wind Energy Areas bought out or under litigation, no federal funding for the port terminal, and no tax credit. Modo Energy's read is blunt: there is a limited credible path for these projects to reach commercial operation by the expected mid-2030s target date.
For California's grid, the math is unforgiving. Offshore wind was supposed to be the clean, high-capacity-factor answer to evening ramps and long-duration shortfalls. Every lease that exits is capacity the state must now find elsewhere, in a queue already crowded with solar and storage competing for the same interconnection.
What to watch: whether the litigation restores any of the leases, and what California's planners pencil in to replace up to 2 GW of Morro Bay capacity that may never get built.
| Category | Buyout amount ($ million) |
|---|---|
| RWE (3 leases, reported) | 1,200 |
| TotalEnergies | 928.3 |
| Invenergy (4 leases) | 765 |
| Golden State Wind | 120 |
Source: Modo Energy Weekly Dispatch, Oct 16, 2026; Marine Log, Jun 18, 2026. RWE figure reported, not officially confirmed.
Sources
- Modo Energy, Weekly Dispatch (Oct 16, 2026): DOI paid Invenergy $765M (announced Jun 17, 2026) to terminate four offshore wind leases (NY Bight, Central Coast CA, Gulf of Maine), funds redirected to gas-fired and geothermal projects; $120M Golden State Wind buyout (Morro Bay Wind Energy Area); RWE reportedly received $1.2B for three leases including Humboldt; $426.7M Humboldt Bay Harbor port grant withdrawn Aug 2025; limited credible path to commercial operation by mid-2030s.
- Marine Log (Jun 18, 2026): Interior in $765M offshore wind buy-out deal with Invenergy; $928.3M TotalEnergies agreement announced March 2026 now facing court challenge. https://www.marinelog.com/offshore/offshore-wind/interior-in-765m-offshore-wind-buy-out-deal-with-invenergy/
- Washington Examiner (Sep 2026): California suing over the Invenergy deal; Invenergy paid $111M+ for the California lease in 2022, planned up to 2 GW. https://www.washingtonexaminer.com/policy/energy-and-environment/4737667/california-sues-trump-over-deal-cancel-offshore-wind-projects/
- ts2.tech (Jun 17, 2026): Trump administration agrees to $765M exit from Invenergy offshore wind leases. https://ts2.tech/en/trump-administration-agrees-to-765-million-exit-from-invenergy-offshore-wind-leases/