The Load Factor Weekly · 2026-W45

Nov 2–8, 2026

63 projects added (16.5 GW), parent companies linked on 22

Published · by the Load Factor team

In the week of Nov 2–8, 2026, 63 projects (16.5 GW) first appeared in the queue data we track daily, 8 withdrew and 5 moved forward. Parent companies were linked on 22 projects. As of Nov 14, 69.7% of 13,456 active queue projects name a developer (two sources agree on 566).

Queue movement

Added
MISO 36 (11.6 GW), ERCOT 27 (4.9 GW)
Withdrawn
PJM 4, MISO 3, SPP 1
Moved forward
PJM 4 to construction, SPP 1 to in service

Developers identified

None this week; parent companies were linked on 22 (MISO 12, West 6, PJM 3, 1 elsewhere).

Examples

Deals

6 deals · 4 M&A, 2 financing

PPA prices

The FERC EQR 2026 Q3 quarter is now in the price and offtaker tables.

Load / data centers

No newly tracked data centers.

Capacity added by ISOGigawatts that entered the queues this week

Sources: Queue movement: daily ISO queue releases through Nov 8 (MISO, PJM from Oct 17; CAISO, ERCOT, ISO-NE, NYISO, SPP from Oct 21); status and identification records applied Nov 2–8, 2026; deals: deal records dated Nov 2–8, 2026; PPA prices: FERC EQR, latest complete quarter 2026Q3; coverage as of Nov 14; data centers: Load Factor's site records (OpenStreetMap, Epoch AI, public records), changes tracked daily from Oct 29; nearby supply: the week's added queue projects within 25 mi. Renewable and unstated-fuel projects; PJM duplicates counted once.

Project IDs open in the Load Factor app.

Questions or tips for the brief? Write to [email protected].