The Load Factor Weekly · 2026-W44

Oct 26 – Nov 1, 2026

58 projects added (13.1 GW), 167 withdrawn, parent companies linked on 687

Published · by the Load Factor team

In the week of Oct 26 – Nov 1, 2026, 58 projects (13.1 GW) first appeared in the queue data we track daily, 167 withdrew and 8 moved forward. Parent companies were linked on 687 projects, and a developer was identified on 1.

Queue movement

Added
MISO 49 (12.3 GW), ERCOT 9 (807 MW)
Withdrawn
MISO 161, PJM 4, SPP 1, ISO-NE 1
Moved forward
PJM 5 to in service, PJM 2 to agreement stage, PJM 1 to construction
1 project announced, not yet in a queue

Developers identified

1 project now names a developer (NYISO 1); parent companies were linked on 687 (West 181, MISO 141, CAISO 116, 249 elsewhere).

Examples

Deals

5 deals · 2 financing, 2 M&A, 1 announcement

Load / data centers

No newly tracked data centers (tracked from Oct 29).

Capacity added by ISOGigawatts that entered the queues this week

Sources: Queue movement: daily ISO queue releases through Nov 1 (MISO, PJM from Oct 17; CAISO, ERCOT, ISO-NE, NYISO, SPP from Oct 21); status and identification records applied Oct 26 – Nov 1, 2026; deals: deal records dated Oct 26 – Nov 1, 2026; data centers: Load Factor's site records (OpenStreetMap, Epoch AI, public records), changes tracked daily from Oct 29; nearby supply: the week's added queue projects within 25 mi. Renewable and unstated-fuel projects; PJM duplicates counted once.

Project IDs open in the Load Factor app.

Questions or tips for the brief? Write to [email protected].

Get the brief every MondayQueue movement, newly identified developers and the week’s deals. Unsubscribe anytime.

All issues

Book a 30-min walkthrough