Queue Deep Dive

Data Centers Are Rewriting MISO's Interconnection Queue

Published September 17, 2026 • 2 min read • Load Factor team
Share this

MISO's interconnection queue has a fast lane now, and data centers built it.

On September 8, MISO's VP of System Planning Aubrey Johnson said every cycle of the fast-track process "is helping us to bring reliability-critical generation online faster." The numbers behind the statement: 58 project submissions totaling nearly 29 GW, with 38 projects (~18 GW) finished negotiating and signed to interconnection agreements, and five more (~3 GW) close behind. MISO expects the collection in service by 2029.

For scale, Load Factor's queue database tracks 1,791 active renewable projects in MISO totaling 303.7 GW — which makes the 29 GW fast-track roughly one-tenth of the entire queue, concentrated into the projects most ready to serve load.

Who is building

The project mix tells the story. NextEra is running a battery campaign across Indiana — Steamboat (500 MW), Merom (500 MW), Crosley (400 MW), Sandcut (350 MW) — aimed at tech-driven load. Northern Indiana Public Service Co.'s 600 MW Malden battery project targets hyperscale campuses including Amazon's expanding footprint. On the gas side, Maple Creek's 641.8 MW Sullivan County combined cycle and the 400 MW Trotman Energy Center are both tied to the Heartland Industrial Park data center campus. In Arkansas, the DOUBLEC Energy Center (400 MW solar + 400 MW storage) will interconnect to the same West Memphis 500-kV line serving Google's $4 billion Project Pyramid campus.

The battery tilt is no accident. In Load Factor's MISO queue data, battery storage is now the third-largest resource by capacity — 60.1 GW across 337 projects, just under 20% of all queued capacity — behind only solar (141.1 GW) and wind (68.5 GW).

Fifth ERAS cycle: project capacity by resource (MW) Capacity (MW)
CategoryGas (MW)Battery storage (MW)Solar + storage (MW)Wind (MW)
DOUBLEC Energy Center (solar + storage)008000
Calcasieu Parish Combined Cycle767.7000
Rapides Parish Combined Cycle756000
Bayou Point Combined Cycle750000
Sullivan County Combined Cycle641.8000
Malden Battery Energy Storage060000
Merom Energy Storage050000
Steamboat Energy Storage050000
Crosley Energy Storage040000
Trotman Energy Center400000
Point Coupee Combined Cycle377000
Sandcut Energy Storage035000
Little Rock Wind000300
Tradewater Energy Storage015500

Source: MISO fifth ERAS cycle announcement, September 8, 2026

Source: MISO fifth ERAS cycle announcement, September 8, 2026. 15 projects totaling ~7.3 GW; 14 listed with disclosed capacities.

The queue rewards readiness now

This is the first-ready, first-served era made concrete. The queue no longer rewards whoever filed first — it rewards whoever can serve load fastest. Across the 1,791 active renewable projects (303.7 GW) Load Factor tracks in MISO, the pattern is unmistakable: storage and hybrid projects positioned near large-load announcements are moving while speculative filings stall. Standalone storage and hybrid projects alone account for 93.1 GW — nearly a third of all queued capacity.

Watch whether this becomes the template. SPP already runs 90-day interconnection studies for large loads paired with generation. If FERC's data-center show-cause orders push other regions the same way, the fast lane stops being a MISO experiment and becomes the national model.

What Load Factor's data shows

  • Sheer scale: 1,791 active renewable projects totaling 303.7 GW are currently sitting in MISO's queue (withdrawn and non-renewable projects excluded), as of September 17, 2026.
  • Storage has arrived: Battery storage is the third-largest resource in the queue at 60.1 GW across 337 projects — just under 20% of all queued capacity — trailing only solar (141.1 GW, 812 projects) and wind (68.5 GW, 445 projects).
  • The fast-track, in context: The fifth ERAS cycle's 29 GW represents roughly one-tenth of the 303.7 GW in the full queue — a concentrated wager on the projects closest to serving load.
  • Flexibility dominates the pipeline: Hybrid projects add another 33.0 GW (162 projects). Together with standalone storage, flexible resources total 93.1 GW — nearly a third of everything queued in MISO.
Renewable queue capacity by fuel, in MISO Capacity (GW)
CategoryCapacity (GW)
Solar141.1
Wind68.5
Battery Storage60.1
Hybrid33
Hydro0.9
Biomass0.1
Geothermal0

Source: Load Factor interconnection queue dataset, as of 2026-09-17

Source: Load Factor queue database, as of September 17, 2026. 1,791 active renewable queue projects totaling 303.7 GW; withdrawn and non-renewable projects excluded.

Sources: MISO September 8 news release (fifth ERAS cycle); Load Factor queue database.

Load Factor tracks 38,000+ interconnection queue projects, withdrawn included, across 16 North American markets, with the evidence behind every developer it names.

Next step

See your market in 30 minutes.

A walkthrough of the projects, developers and evidence in the markets you work in.

Get the weekly brief

Queue movement, newly identified developers and the week’s deals, every Monday. Read past issues

Book a 30-min walkthrough