Check planned transmission
Use the Transmission tab to see planned high-voltage lines, their cost, timing and status, and how many queue projects each one affects.
- Web app
- Updated
Overview
Transmission lists planned high-voltage lines: their portfolio, voltage, cost, length, states, target in-service date, status, developer, and how many queue projects each one affects. New lines can open a market to projects that are stuck in the queue today, so this is where to see which ones are coming.
Steps in this video
- Step 1: Filter by portfolio
- Step 2: Sort by cost, voltage or length
- Step 3: See how many queue projects each line touches
What's covered
The tab covers regional transmission portfolios approved by grid operators, starting with MISO's Long Range Transmission Planning portfolios (Tranche 1 and Tranche 2.1). The cards at the top total each portfolio: the number of lines, the cost, the voltage and the in-service years.
Find lines
- Portfolio: pick one in the list above the table.
- Resolution: narrows by the developer's confidence level for the projects affected.
- Sort by any column (cost, kV, miles, target date, queue impact).
Read a row
| Column | What it shows |
|---|---|
| Name | The line, by its end points. |
| Portfolio | The plan it belongs to (for example T1 or T2.1). |
| kV | Voltage. |
| Cost ($M) | The estimated cost. |
| Miles | Length, where published. |
| States | The states it crosses. |
| Target ISD | The target in-service date. |
| Status | Planned, in progress and so on. |
| Developer | The company building it, once awarded. |
| Queue impact | How many queue projects are near the line. |